Progress Report from Acton
- No 27 Pastoral
- Jul 2
- 1 min read
Progress at Acton!
95km cleared and graded
68 trough pads concreted (12 to go!)
Booster pump constructed
1 of 6 poly tanks built
Now to unroll, weld and bury some poly!! Certainly takes a few hands to keep this project moving, particularly on winter mornings when trying to flex the 90mm pipe into position to weld.
Great crew, exciting times!